Frisco Is Rebuilding Toyota Stadium and Betting $1 Billion Around It

By Harrison Alley · The Collin County Post · from City of Frisco council presentation and news releases, Sept. 17, 2024 and Oct. 20, 2026; Hunt Sports Development announcement via Business Wire, Sept. 22, 2026; Sports Business Journal, Sept. 22, 2026; Texas Comptroller mixed beverage receipts (data.texas.gov), 2015 to 2026; MLSSoccer.com. · November 21, 2026

FC Dallas opened its playoff run on Saturday afternoon with a 3-0 win over the Portland Timbers at Toyota Stadium, in a stadium with its west and north sides closed and under construction. It was the first game of a best-of-three series, and it doubled as a progress report: the east side of the stadium reopened in September after a full rebuild, and the rest of the work runs through the 2027 season. Game 2 is Nov. 28 in Portland. If Portland wins it, Game 3 comes back to Frisco on Dec. 2, construction and all.

The playoff game is a sideshow to the larger project. Toyota Stadium is midway through a renovation whose price has grown past $215 million, and around it Frisco has approved a hotel, a convention center and an office district that the city expects to top $1 billion in private investment. It is the same play the city is running at Fields West, at larger scale and with a team already in residence. Our Collin County playoff tracker follows the high school side of the postseason; this is the professional one, and its venue is a construction site.

A stadium Frisco owns

Toyota Stadium opened on August 6, 2005, as Pizza Hut Park, the third soccer-specific stadium in Major League Soccer. The 145-acre complex at Main Street and World Cup Way is owned by the City of Frisco and run with the Hunt family, which owns FC Dallas. Frisco ISD has played games there since 2005, the NCAA's FCS championship game has been held there 15 straight years, and the National Soccer Hall of Fame opened at the stadium's south end in 2018 as part of a $55 million renovation. Toyota has held the naming rights since 2013 and renewed them in October 2025.

The deal, and the growing price tag

On September 17, 2024, the Frisco City Council approved agreements that extended the FC Dallas lease and funded up to $182 million in stadium improvements: 3,400 additional seats, a shade structure over the bowl, upgraded clubs and suites, and new broadcast and press areas. The lease now runs through the end of 2057. The approved funding split:

SourceAmount
Tax increment reinvestment zone (City of Frisco and Frisco ISD)$77 million
Frisco Community Development Corporation$40 million
The Hunt family$65 million
Total approved, 2024$182 million

Who pays for the renovation: the 2024 deal

$77MTax increment zone$40MFrisco CDC$65MHunt family

The tax increment reinvestment zone is funded by the City of Frisco and Frisco ISD. The Hunts pay every dollar above the $182 million approved total; by September 2026 the announced cost had passed $215 million.

The price has not held. The 2024 agreements make the Hunts responsible for any costs above $182 million, and by September 2026 the project's own announcements were calling it "the $215 million renovation," with no public breakdown of the increase.

What is being built

The rebuilt east side opened in September 2026 while work continues on the north and west sides. The east side brought a 12,000-square-foot East Side Club and 1,800 new seats, under a finished section of the new roof. With the west and north concourses closed this fall, the stadium is playing at reduced capacity. The full stadium is scheduled to be complete in the spring of 2028, in time for that season's first home game.

The district around it

The stadium work is the anchor for a district on the surrounding parking lots and land. The 2024 master development agreement carries incentives for mixed-use development expected to bring more than $1 billion in private investment. On the east side, Hunt Sports Development announced a partnership with Peak Curated Development and VENU Holding Corporation on September 22, 2026: a boutique hotel of about 290 rooms, more than 40,000 square feet of convention and event space, a 15,000-square-foot ballroom that converts into a 3,000-person music hall, a rooftop bar, restaurants, a spa and a fitness center. Groundbreaking is slated for 2027. Sports Business Journal puts the full project at 32 acres and $1.3 billion, with the development agreement requiring at least $110 million of office investment and $231 million across the hotel, retail and multifamily pieces.

On October 20, 2026, the City Council voted unanimously to sign a Chapter 380 economic development agreement with the hotel's developer, D96 Hotel & CC, LLC. The agreement describes the project somewhat differently from the announcement: a 250-room full-service upscale hotel, 15,000 square feet of convention meeting space, 30,000 square feet of restaurants and retail, and a shared parking garage. The city will return half of the city hotel occupancy tax the hotel collects for ten years, capped at $5 million, waive half its development fees, and pass through state hotel-project funds. Both descriptions are reported here as published; the developers have not reconciled them in public.

On the west side, FC Dallas and Cawley Partners are planning a Class A office campus designed by Gensler that would ultimately exceed one million square feet. The first phase is expected to be complete in 2028.

The matchday economy is already there

The development is not landing in a vacuum. In the Texas Comptroller's alcohol sales records, the bars and restaurants on Main Street, Coleman Boulevard, Frisco Square Boulevard and World Cup Way filed $8,237,133 in sales in 2026 through October, the stadium district's biggest year on record, from 20 businesses. The biggest seller is Rollertown, the roller rink and bar at 6450 Main Street, at $2,532,087. Second is Toyota Stadium itself, at $1,014,390, sold while half the building was closed. The Derbyshire at Frisco Square filed $889,703, Rotate Bar & Kitchen $690,024 and Anchor Bar $657,095, with Eight 11 Place ($274,186) and Jake's Burgers & Beer ($216,633) further down Main Street.

Alcohol sales in the stadium district, 2015 to 2026

$6.3M2015$7.4M2016$7.5M2017$5.5M2018$6.9M2019$3.4M2020$5.7M2021$7.1M2022$6.8M2023$7.2M2024$7.0M2025$8.2M2026

Bars and restaurants on Main Street (blocks 5300 to 7700), Coleman Boulevard, Frisco Square Boulevard and World Cup Way. The pale bar is the pandemic year, 2020. 2026 runs through October and is already the district's biggest year on record. Source: Texas Comptroller mixed beverage receipts.

YearStadium district filersDistrict salesAll Frisco sales
201514$6,337,179$49,010,157
201919$6,877,613$72,484,817
202322$6,813,210$119,590,032
202523$6,967,454$126,599,611
2026 (through Oct)20$8,237,133$107,125,277

The names on the doors have turned over along the way. The British Lion Pub, an FC Dallas pub partner on Main Street, closed, and its suite is now Rotate Bar & Kitchen, the district's fourth-biggest seller. The Frisco Square space that has cycled through several restaurants is now The Derbyshire, its third-biggest. The district's sales dipped to $3,409,846 in the pandemic year of 2020 and have climbed since, passing their pre-pandemic level even as the stadium shrank around construction. That is the base the hotel, music hall and offices are being built on: a matchday economy that already exists, next door to a $215 million construction site.

What happens next

FC Dallas plays Game 2 in Portland on Nov. 28; a Portland win brings Game 3 back to Toyota Stadium on Dec. 2, and a Dallas series win sends the club to a conference semifinal on Dec. 5 or 6. Off the field, the east-side district breaks ground in 2027, the stadium finishes in the spring of 2028, and the first west-side offices are expected the same year. The hotel and convention center run on the longest clock: the master development agreement gives the first phase until the end of 2037 to be completed.

Toyota Stadium: 2005 to 2037

2005  Opens as Pizza Hut Park, the third soccer-specific stadium in Major League Soccer

2013  Toyota takes the naming rights (renewed in 2025)

2018  National Soccer Hall of Fame opens at the south end, part of a $55 million renovation

2024  The $182 million deal: renovation funded and the FC Dallas lease extended through 2057

2025  Renovation groundbreaking, in March

2026  The rebuilt east side reopens in September; the surrounding district is announced

2027  The east-side hotel and convention district breaks ground

2028  The full stadium is complete in the spring; the first west-side offices are expected the same year

2037  The district's first phase is complete under the development agreement

Collin County rankings and roundups

The Post's data stories, bar and restaurant rankings, construction leaderboards, school and housing reports, plus our regular Collin County roundup of what's opening, what's under construction, and what's worth trying.

Renovation costNow $215 million plus; approved at $182 million in 2024
Who pays$77M tax zone (city and Frisco ISD), $40M Frisco CDC, $65M Hunt family; Hunts cover overruns
LeaseFC Dallas at Toyota Stadium through 2057
Seats added3,400
East sideReopened September 2026
Full stadiumComplete spring 2028
Hotel250 rooms in the October 2026 city agreement; about 290 as announced in September
OfficesMore than 1 million sq ft planned on the west side
District alcohol sales$8.24 million in 2026 through October, a record for the stadium area

Alcohol figures are Texas Comptroller mixed beverage receipts for Main Street (blocks 5300 to 7700), Coleman Boulevard, Frisco Square Boulevard and World Cup Way, all permit types; 2026 runs through October, the latest filings available. Hotel figures differ between the September 2026 developer announcement and the October 2026 city agreement; both are reported as published. Correction: an earlier version of this story understated the district's alcohol sales because of an incomplete data pull on our side. The figures have been replaced with a complete pull from the Comptroller's records. On November 22, 2026, the district and city totals were recomputed from the complete filing history; the 2020 and 2025 figures moved by about 1 percent or less.

HA
About the publisher

Harrison Alley

Harrison Alley is a Dallas-based publisher and data enthusiast. He built the Collin County Post to read Collin County's public filings, sales-tax permits, liquor licenses, construction registrations, and appraisal records, and turn them into local news, updated as the records land. He also publishes Fast Food Index, which tracks weekly menu prices at more than 55,000 U.S. restaurants.