Frisco's $3 Billion Mix Rises on the Hole That Ate Wade Park

By Harrison Alley · The Collin County Post · from City of Frisco and Frisco EDC records, the developer's plans and the federal court record · November 18, 2026

For a decade, the most famous thing at Lebanon Road and the Dallas North Tollway was a hole. Wade Park, a $2 billion plan for office towers, shops, homes and a Whole Foods, stopped construction in 2017 and left behind two unfinished buildings and a flooded excavation pit so notorious it earned a nickname: the hole on the toll.

The Mix as planned, animated from the developer's renderings. Rendering: The Mix.

That hole is now the foundation of the largest development under construction in Collin County. The Mix, a $3 billion, 112-acre district from New York-based JVP Management and its affiliate The Mix Partners, LLC, broke ground on January 16, 2025, and its first underground parking garage is being built directly into the old Wade Park excavation.

Rendering of The Mix in Frisco at dusk, with retail storefronts and the project's office tower behind

Rendering: The Mix.

What $3 billion builds

At full buildout, the developer's plan calls for more than 2 million square feet of Class A office space, 375,000 square feet of retail, 3,299 homes and two hotels, a 400-room business hotel with meeting space and a 150-room boutique hotel overlooking the park. The centerpiece is a central park (9 acres in the developer's plan) designed by OJB, the landscape firm behind Klyde Warren Park in Dallas, within 16.5 acres of open space.

Watercolor rendering of The Mix central park in Frisco at sunset, ringed by residential towers

The central park as planned. Rendering: The Mix.

Phase 1 covers 28 acres: a 114,000-square-foot office building (the city's agreement describes it as medical office; the developer markets it as a boutique headquarters opportunity), a 40,000-square-foot grocery store, 33,000 square feet of retail, 630 homes, and a 2,250-space underground garage inside the old pit. JVP partner Van Nguyen has estimated repairing the hole alone could cost up to $85 million; the Wade Park-era retaining walls are still in place, but the foundation work must essentially be redone.

The grocer is Whole Foods Market, Frisco's first, announced July 24, 2025. It is a homecoming of sorts: Whole Foods was also Wade Park's planned grocer, and development head Tim Campbell noted the company "has remained committed to this site and Frisco for more than 10 years."

The city's $113 million is pay-for-performance

Frisco's City Council unanimously approved a Master Development Agreement on October 15, 2024, offering up to $113.4 million in performance-based grants from the city, the Frisco Economic Development Corporation and the Frisco Community Development Corporation. None of it is paid up front: the money flows only when the Phase 1 components, the office building, the grocer, the retail, the 630 homes and the garage, are actually completed. A separate $10 million piece accelerates the grocery store. Mayor Jeff Cheney put the condition plainly at approval: the deal "requires the developer to deliver the underground parking garage before any incentives are paid."

The deadlines are close. All Phase 1 infrastructure is due complete by the end of 2026, weeks from now. The grocery store and 80% of the retail must be open by the end of 2027, and the first phase is expected to open in 2028.

How Wade Park collapsed

Atlanta developer Stan Thomas assembled roughly 176 acres at the Tollway and Lebanon between 2012 and 2015 and started building Wade Park in 2014. By early 2017 the project's loans were maturing; Thomas took an ~$83 million bridge loan from Gamma Real Estate Capital in January 2017, a deal that also gave Gamma a 75% ownership stake in the project's holding entity, a provision Gamma called "the Hammer," according to the federal court record.

Gamma declared a default in January 2018. After six forbearance agreements, the Thomas entities handed the deeds to Gamma in February 2019 in exchange for about $140.1 million in debt relief. JVP Management took control of the site later in 2019. The land entities filed Chapter 11 after the handover, and the ensuing fraudulent-conveyance lawsuit against Gamma was dismissed, a dismissal the U.S. Court of Appeals for the Second Circuit affirmed on June 17, 2024.

What's happening on the site now

Construction passed its one-year mark in mid-2026, with excavation and structures visible from the Tollway. The freshest paperwork is small but telling: on November 11, 2026, the developer registered a $1.5 million build-out of The Mix Marketing Center at 5302 Dallas Parkway, the on-site leasing office for Phase 1, with work scheduled to run from November 30, 2026 through March 22, 2027, read that report.

If the end-of-2026 infrastructure deadline holds, the next public milestone is the grocery store rising through 2027, on the exact corner where Frisco's most famous hole sat empty for the better part of a decade.

Sources: Frisco Economic Development Corporation, Master Development Agreement · The Mix (developer) · Second Circuit opinion summary, Cleary Gottlieb · Bisnow, October 16, 2024 · The Frisco News, September 24, 2025 · Texas Department of Licensing and Regulation filing TABS2027005630

Collin County rankings and roundups

The Post's data stories, bar and restaurant rankings, construction leaderboards, school and housing reports, plus our regular Collin County roundup of what's opening, what's under construction, and what's worth trying.

Development cost$3 billion
Site112 acres at Lebanon Road & Dallas Parkway
OfficeMore than 2 million square feet planned
Retail375,000 square feet
Homes3,299 units
HotelsTwo: a 400-room business hotel and a 150-room boutique hotel
Central park9 acres, designed by OJB, the Klyde Warren Park firm
Grocery anchorWhole Foods Market: Frisco's first
DeveloperThe Mix Partners, LLC (JVP Management)
City incentivesUp to $113.4 million, performance-based
GroundbreakingJanuary 16, 2025
Phase 1 openingExpected 2028

Project figures come from the developer's published plan, the Frisco Economic Development Corporation and the federal court record in the Wade Park litigation. Two figures differ between sources: the developer describes a 9-acre central park and 550 hotel rooms in total, while Community Impact has described an 8-acre park and D CEO a 650-room total; the Post uses the developer's figures. Renderings are the developer's conceptual drawings, published by The Mix.

HA
About the publisher

Harrison Alley

Harrison Alley is a Dallas-based publisher and data enthusiast. He built the Collin County Post to read Collin County's public filings, sales-tax permits, liquor licenses, construction registrations, and appraisal records, and turn them into local news, updated as the records land. He also publishes Fast Food Index, which tracks weekly menu prices at more than 55,000 U.S. restaurants.

Discussion

Comments are for email subscribers, it keeps the discussion local and spam-free, and subscribers get an email when someone replies to them.

← All Collin County filings · Rankings · Republish this story free · More Frisco news