McKinney's $200 Million Cannon Beach Surf Resort Is Under Construction for 2027
A beach is under construction in McKinney. Cannon Beach, a $200 million surf resort on 35 acres at the northeast corner of Stacy Road and State Highway 121, broke ground in December 2025, and its first phase is projected to open in late 2027, a surf lagoon, a 150-room hotel and a sand beach in the middle of North Texas.
The Cannon Beach site as planned, animated from the developer’s rendering. Rendering: Cannon Development, via the McKinney Community Development Corporation board packet.
Rendering: Cannon Development, via the McKinney Community Development Corporation board packet.
What is being built
The centerpiece is the water. The developer’s plan centers on a 3-acre surf pool under the Revel Surf banner, powered by Swell MFG wave technology, the same pairing behind the Cannon group’s park in Mesa, Arizona, which opened in 2024, plus a cliff-diving lagoon, a standing wave, a skate pump track and a larger beach than the Arizona original. Around the water: a 150-room resort hotel with a rooftop pool, 35,000 square feet of retail, and a flex entertainment building of about 105,000 square feet planned for bowling, multi-level electric karting and a movie theater.
Rendering: Cannon Development, via the McKinney Community Development Corporation board packet.
The developer is Cannon Development Company Texas, LLC, and the architect is Cross Architects of Plano. The McKinney Economic Development Corporation assembled much of the land along the corridor; its president has described Cannon Beach as a $200 million investment expected to draw 300,000 visitors a year and support about 700 jobs.
The votes and the money behind it
The city’s development corporations backed the project early. On February 27, 2025, the McKinney Community Development Corporation approved a $4 million grant to Cannon Development for infrastructure improvements on the site. The zoning took longer: a surf park was not a use listed in McKinney’s code, so the project needed its own planned development district. The Planning and Zoning Commission recommended approval 7–0 on March 10, 2026, and the City Council approved the rezoning of the roughly 58-acre tract on April 21, 2026.
What happens next
Visit McKinney’s project timeline has site work and lagoon excavation under way through 2026, vertical construction on the hotel, beach club and entertainment buildings in 2027, and the surf lagoon and beach as the opening act of phase 1 in late 2027. The pieces are already surfacing in state construction records: in November, the Post tracked a $150,000 state filing for the park’s filtration room No. 3, with elevated wave controls, at 6350 SH 121, read that report. The Post will keep following the filings as the build moves.
Sources: the developer’s February 2025 presentation to the McKinney Community Development Corporation · City of McKinney meeting records · Visit McKinney
The Post's data stories, bar and restaurant rankings, construction leaderboards, school and housing reports, plus our regular Collin County roundup of what's opening, what's under construction, and what's worth trying.
Project figures come from the developer's February 2025 presentation to the McKinney Community Development Corporation, City of McKinney records and Visit McKinney. One figure differs between sources: the developer's plan shows a 3-acre surf pool, while Visit McKinney describes a four-acre surf lagoon; the Post uses the developer's figure. Renderings are the developer's conceptual drawings, published in the MCDC board packet, the finished project may differ from the drawings. Opening dates are projections and construction schedules change.
← All Collin County filings · Rankings · Republish this story free · More McKinney news
Discussion
Comments are for email subscribers, it keeps the discussion local and spam-free, and subscribers get an email when someone replies to them.